id,summary,reporter,owner,description,type,status,priority,component,severity,resolution,keywords,cc,release
10127,[PATCH] if the milestone due date is the only given date at all_ ALAP scheduling must use it as end date of last successor ticket,falkb,ChrisNelson,related to #9705.\r\n\r\nI have several tickets grouped with parent tickets. They all don't have any dates set at all. The only date set is the milestone due date.\r\n\r\nALAP scheduling only works well if I apply this patch:\r\n{{{\r\n#!diff\r\nIndex: tracjsganttplugin/0.11/tracjsgantt/tracpm.py\r\n===================================================================\r\n--- tracjsganttplugin/0.11/tracjsgantt/tracpm.py	(revision 11706)\r\n+++ tracjsganttplugin/0.11/tracjsgantt/tracpm.py	(working copy)\r\n@@ -619_8 +619_7 @@\r\n                 if self.isCfg(['pred'_ 'succ']):\r\n                     pred = []\r\n                     for t in tickets:\r\n-                        if not t['children'] and \\\r\n-                                t['milestone'] == row[0] and \\\r\n+                        if t['milestone'] == row[0] and \\\r\n                                 self.successors(t) == []:\r\n                             if self.isField('succ'):\r\n                                 t[self.fields[self.sources['succ']]] = \\\r\n}}}\r\n\r\nWithout this patch_ "today" is used as end date of the last successor and the scheduled plan starts in the past_ which is completely wrong.,defect,new,normal,TracJsGanttPlugin,major,,,,0.11