10589,partially completed tasks should be remainghours long,maikb,ChrisNelson,Using the !TimingAndEstimationPlugin_ the length of each task seems always to be fixed to estimatedhours. This causes the following miss behaviour:\r\n\r\n- Using ASAP scheduling_ succeding tasks of an incompleted task start to late. [[BR]]\r\n- Using ALAP scheduling_ incompleted tasks start in the past even if the are on-time. [[BR]]\r\n- In any case_ the plan does not include any delay (remaininghours > estimatedhours).\r\n\r\nTo calculate the percentage of completion_ totalhours/estimatedhours still could be used. Thus_ completion = 100% and remainghours > 0 indicates that a task is to late. But you still would see the actual estimated remaining effort (remainghours = delay).,defect,new,normal,TracJsGanttPlugin,normal,,,falkb,0.12