id	summary	reporter	owner	description	type	status	priority	component	severity	resolution	keywords	cc	release
10589	partially completed tasks should be remainghours long	maikb	ChrisNelson	Using the !TimingAndEstimationPlugin, the length of each task seems always to be fixed to estimatedhours. This causes the following miss behaviour:\r\n\r\n- Using ASAP scheduling, succeding tasks of an incompleted task start to late. [[BR]]\r\n- Using ALAP scheduling, incompleted tasks start in the past even if the are on-time. [[BR]]\r\n- In any case, the plan does not include any delay (remaininghours > estimatedhours).\r\n\r\nTo calculate the percentage of completion, totalhours/estimatedhours still could be used. Thus, completion = 100% and remainghours > 0 indicates that a task is to late. But you still would see the actual estimated remaining effort (remainghours = delay).	defect	new	normal	TracJsGanttPlugin	normal			falkb	0.12