id,summary,reporter,owner,description,type,status,priority,component,severity,resolution,keywords,cc,release
6973,Can't import dates from Trac to Project,Chris.Nelson@SIXNET.com,okazaki,I have tried setting Start (due_assign) and Finish (due_close) to "2010-01-02" and "2010/01/02" and the dates still come through as today.  What format should those fields take?\r\n\r\nAlso_ if percent complete an integer or a fraction?  That is_ if something is half done_ should complete be .50 or 50?,defect,assigned,normal,VisualBasicTracConnectorIntegration,normal,,,,0.11