id,summary,reporter,owner,description,type,status,priority,component,severity,resolution,keywords,cc,release
9279,start date in chart different to set start date in ticket,falkb,ChrisNelson,I have a ticket which is parent of other tickets and it has set fields.start and fields.finish. I understand both fields as they are for setting the __planned__ range of time.\r\n\r\nBut the chart don't display the given start date in column "Start Date" correctly_ but it seems to compute a new start date from "End Date" minus worked hours. That confuses us when reading the chart as plan.\r\n\r\nBTW: on several places it's not clear in the chart what is just data of plan/schedule and what is data of the past reality. This should be clearly distinguished by the chart_ maybe by colors. This is somehow related to #8786.,defect,new,normal,TracJsGanttPlugin,normal,,,rjollos,0.12