id	summary	reporter	owner	description	type	status	priority	component	severity	resolution	keywords	cc	release
9705	In ALAP scheduling, today is not a valid end date if no dates are assigned	ChrisNelson	ChrisNelson	Any unspecified date defaults to today but if no dates are specified, an ALAP schedule works backwards from the end, gives the last task today as a due date then works into the past.  But we can't work in the past so that's not a great choice.\r\n\r\nUnfortunately, we don't know the makespan of the project before starting so we can't easily say "today plus makespan" as the starting point.\r\n\r\nThis should be fixed, even though I don't know how right now.	defect	new	normal	TracJsGanttPlugin	normal			falkb	0.11