id	summary	reporter	owner	description	type	status	priority	component	severity	resolution	keywords	cc	release
9833	Scheduling Ignores Milestones	RobertII	ChrisNelson	When scheduling as late as possible, tasks should be scheduled to complete no later than their milestone.  Currently, it seems to be ignored, so that tasks are sometimes scheduled to (start and) finish after their milestone.\r\n\r\nObviously, if the milestone has no date, or a successor has an earlier "latest start date", or a parent has an earlier finish date, then that should take priority.  \r\n\r\n\r\n\r\n\r\n\r\n	defect	assigned	high	TracJsGanttPlugin	major			mike.kronenberg@kronenberg.org	0.12