  • ProjectManagementIdeas

    v138 v139  
    465465   * risk - Riskier work goes first.
    466466   * work - A function may favor short tasks ("low hanging fruit") or long ones (which inherently have more risk).
    467    * task type -Ffix bugs before doing new features.
     467   * task type - Fix bugs before doing new features.
    468468   * percentComplete - Finishing something that's partially done is better than starting something new.
    469469   * "fit" - It is better to start a 2-day task on Wednesday and hold a 4-day task for the next week than to break up the longer task across a weekend.