ProjectManagementIdeas
v27 v28 279 279 280 280 Packaging design and circuit board layout are so short -- relative to other activities -- they speeding them up doesn't really help the project. But if we could shorten schematic design or firmware, every day we take out of one of those activities we also take out of the project schedule. 281 282 == Sub-tasks == 283 284 To manage the complexity of the chart, we can break tasks down into sub-tasks and show various levels of detail. 285 286 [[Image(roll-up-1.PNG)]] 287 288 [[Image(roll-up-2.PNG)]] 289 290 281 291 == Plan of attack == 282 292