100 | | For such a short task list we can manually inspect and see that firmware (40h) follows circuit board (16h) follows schematic (24h) and the shortest project time is 80 hours (two weeks) and we can take two weeks from the milestone date to know when we have to start work to finish on time. However, a project of any complexity may have many, many more tasks and manual inspection is impractical. With just !TimingAndEstimation and !MasterTicket, we can begin to do more effective project management if we have a task scheduler than can work backwards from the milestone, consider work and dependencies, and calculate task start and end dates and project start date. |
| 100 | For such a short task list we can manually inspect and see that firmware (40h) follows circuit board (16h) follows schematic (24h) and the shortest project time is 80 hours (two weeks) and we can take two weeks from the milestone date to know when we have to start work to finish on time. However, a project of any complexity may have many, many more tasks and manual inspection is impractical. |
| 101 | |
| 102 | With just !TimingAndEstimation and !MasterTicket, we can begin to do more effective project management if we have a task scheduler than can work backwards from the milestone, consider work and dependencies, and calculate task start and end dates and project start date. |
105 | | ||1||Design the Schematic||24h||||May 2|| |
106 | | ||2||Design the Circuit board||16h||1|May 4||| |
107 | | ||3||Design the packaging||16h||||May 4|| |
108 | | ||4||Write firmware||40h||1||May 4|| |
109 | | ||5||Assemble units||8h||2,3,4||May 5|| |
| 107 | ||1||Design the Schematic||24h||||May 5, 2009|| |
| 108 | ||2||Design the Circuit board||16h||1||May 10, 2009|| |
| 109 | ||3||Design the packaging||16h||||May 10, 2009|| |
| 110 | ||4||Write firmware||40h||1||May 10, 2009|| |
| 111 | ||5||Assemble units||8h||2,3,4||May 11, 2009|| |