[[PageOutline]] Trac is strong in basic, individual and small-team task management but lacks features for heavy-duty project management ''a la'' Microsoft Project, Project Manager Workbench, etc. This page discusses those missing features and how they can best be realized. = Gantt Charts = As discussed in [http://groups.google.com/group/trac-users/browse_thread/thread/83c0b6a248040542?hl=en two] [http://groups.google.com/group/trac-users/browse_thread/thread/3084796acbc7233c/3f393a18f99cfebd?hl=en&tvc=2#3f393a18f99cfebd threads] on the Trac Users mailing list, a fundamental requirement for project management is a [http://en.wikipedia.org/wiki/Gantt_chart Gantt chart] to show [http://en.wikipedia.org/wiki/Work_breakdown_structure work Breakdown Structure] (WBS). Trac has three Gantt chart plugins: [wiki:FlashGanttPlugin FlashGantt]:: seems complex and stale. [wiki:GanttChartPlugin GanttChart]:: is a very simple Gantt chart implemented in a formatted text region. It is manually edited, not data-driven. [http://willbarton.com/code/tracgantt/ TracGantt]:: has potential but has some funky fields (e.g., Due to Assign) that don't seem to be appropriate to what we want to do with a Gantt chart. There is a [http://www.viewpath.net/Website/ganttcharts/googlegadget.aspx Google Gadget Gantt chart] which might be leveraged for the visualizations once the data is made available (e.g. using [https://opensvn.csie.org/traccgi/swlcu/wiki/En/Devel/TracGViz/ TracGViz plugin]). That widget is developped and maintained by a company (i.e. [http://www.viewpath.net/ ViewPath]). Besides users need access to the internet and their projects environments '''have to''' be available too so that the iGoogle container be able to retrieve the data to display in the chart. All this means that local deployments (intranets, ...) are not possible. = Requirements = == Gantt Chart Components == In its most basic form, a Gantt chart shows: Tasks:: Self-contained units of work Dependencies:: Relationships between tasks that constrain when they can be done Milestones:: Dates by which one or more tasks must be completed It may also show resource assignments and progress in tasks. It often includes a "today" line to show where a project stands. (If the project is on schedule, all tasks to the left of ''today'' are complete and any task that spans ''today'' has a progress bar to the right of ''today''.) A Gantt chart may also show slack time for tasks, how much they can slip before affecting the overall schedule. == Component Data == Each Gantt chart component or feature requires data to support it. For Trac-based project management, this data is often in addition to the core ticket data. === Core Fields === Core ticket fields include: * type (bug, task, enhancement, etc.) * time (when the ticket was created) * owner (who is working on it) {{{ owner is duplicated. Is it core or additional field ? }}} * reporter (who wrote the ticket) * milestone (what milestone this ticket is part of) * status (new, assigned, ..., closed) * summary (short description) Core milestone fields include: * name * due (date and time) * completed (treated as a Boolean: open or closed) * description === Additional Data === For a simple Gantt chart, we may use the following ticket fields: * owner (the resource assigned to the task) * milestone (when the task is due) * summary (short description) In addition, a task must have: * estimate (expected work require to complete task) * percent complete * dependencies It may also prove useful to note that a resource may not be applied 100% to a task. === Timing === While Gantt charts typically show percent complete, this can be computed from hours remaining vs. total estimate or hours worked vs. total estimate. We will not, necessarily, store percent complete. It is intuitive for display and analysis but difficult for data entry. === Dependencies === Project management generally involves four types of dependencies between tasks or activities: Finish-to-Start (FS):: Task B cannot begin until task A is complete. This is the most common. When building a house, the walls cannot be put up until the foundation is complete. Start-to-Start (SS):: Task B cannot begin until after task A begins (though they may end independently). When building a house, interior painting cannot begin until the dry wall is started. (Each room can be painted as soon as its dry wall is up.) Finish-to-Finish (FF):: Task B cannot end until task A ends (though they may begin independently). When building a house, inspections cannot be completed until construction has completed (though parts may be inspected before the whole job is done). Start-to-Finish (SF):: Task B cannot end until Task A begins. When building a house, the builder may begin getting interim payments during construction but payment will not be completed until the owner can start moving in. In addition, managing the complexity of a large project requires breaking large tasks into smaller ones (or viewing groups of small tasks as larger aggregates). For example, interior painting might be broken down into paint the living room, paint the dining room, etc. While useful, the FF and SF dependencies are somewhat more esoteric than the others and implementation may be deferred. = Features = A Gantt plugin for Trac should analyze ticket dependencies and produce an interactive, explorable Gantt chart showing task progress and project status. By "project", I mean a set of related milestones. Perhaps a software project has a Design Phase, an Alpha Release, a Beta Release, and a General Release. Each would be a milestone with a target date and tickets to complete the work for that milestone. There must be a way to specify which milestones to include either listing explicitly or by giving a pattern or substring filter. == What do we need in the backend ? == The chart should be able to show all tickets (though that may be a very complex chart) or alternately all those tickets matched by a (query | report) or any other ticket group provider. To effectively display project progress, tickets must have estimated and actual times as in the TimingAndEstimation plugin. It is also desirable to have loop detection to error-proof the tool used to create dependencies. It would be nice to be able to choose an As Late As Possible or As Soon As Possible algorithm for laying out tasks. == What do we need in the user interface ? == A "chart these" button on a report page would be very nice. Tasks in the chart should be links to the tickets they represent (preferently opened in a separate tab | window). Milestones should be displayed in the chart as well The chart should support interactively "folding" groups of tasks to hide detail. Zooming in order to see the WBS in more detail Panning or scrolling in order to display the schedule at a different time. Each task's bar in the chart should show actual hours. The chart should have a Today line The chart (or an accompanying report or tool) should aid in resource leveling by (at least) showing overcommitted resources. Visual indications about delays, task completion and other significant events Drag n' Drop so that users can change the order of the tickets (yes, I'm drunk ... hip .o: ) = Related Work = MasterTicketsPlugin supports ''starts after''/''ends before'' dependency (but calls it ''blocks'' and ''blocked by''). The [http://trac.edgewall.org/wiki/SubTickets SubTickets] page talks about adding ''composed of''/''part of''-type dependency. Can this be done in a plugin like !MasterTickets or must it be in the core? TimingAndEstimationPlugin and TracHoursPlugin add estimated and actual hours fields to tickets. There is some disagreement about whether the estimate is the remaining time (so total estimated time is actual + estimate) or total time (so remaining time is estimate - actual). A Gantt chart typically wants estimate and percent complete. It is possible to extract this from either recording convention and we should likely allow either convention via a configurable interface. = Design guidelines = In order to agree about how to implement this functionality, the very first step should be to describe the possible(s) architecture(s) (i.e. how the different components are going to interact with each other since the moment the request is sent by the client until the Gantt chart is rendered by the browser) that will be considered. == Components == In order to add flexibility to the final solution, the '''MVC pattern''' ''should'' be considered during its development. Hence the following components need to be implemented in order to add Gantt charts to Trac. === The Model === It provides the data in the Gantt chart and is not just a single element but a set of components like the following : * The ticket models, which provide data about the issues found in the project environment * Trac query mechanism which provides a way to select (filter) the tickets being shown. * [#RelatedWork Other plugins] used to track ticket dependencies * [#RelatedWork Other plugins] used to track task/subtask relationships * [#RelatedWork Other plugins] used to estimate the time needed to finish the given tasks * Maybe one (a few) component(s) whose role is to provide the functionality specific to Gantt charts, thus acting as a central access point and a mediator so as to put all the other components together. === The View === It ''should'' be a JavaScript component (is this possible ?) responsible for rendering the data provided by ''the model''. Besides it ''might'' support [#Whatdoweneedintheuserinterface other dynamic features] === The Controller === {{{ ¿What do we need this for? }}} === Implications === The aforementionned separation ''should'' allow the replacement of any of the components involved. Hence the following modifications ''should'' be made easily (the list being intentionally incomplete) : - Replace the JS-based view by another made with Flash. - Use a custom, or specific estimation strategy. = Roadmap = There seems to be a consensus that grandiose project management features for Trac should be implemented with a combination of plugins which provide useful functionality on their own. The following plan assumes that approach. 1. Fork !MasterTickets as !TicketDep (or something) and add ''composed of''/''part of'' dependencies and [http://trac.edgewall.org/wiki/SubTickets#CreatingSubtickets means to create them]. Plan for but do not yet implement ''starts with'' and ''ends with'' dependencies. 1. Specify the interfaces necessary for a scheduling plugin to use dependencies, estimates, and time worked to determine project schedule. * Consider adding a percentage available when scheduling resources. 1. Specify the interfaces necessary for a Gantt chart to get data from tickets. * Each task must have a name, duration, percent complete, and start or end. (The start or end comes from schedule calculations, not direct ticket data.) * Access to dependencies between tickets is also needed so as to render the chart. 1. Implement those interfaces on top of TimingAndEstimationPlugin. = Disclaimer = The bulk of this page was prepared by Chris Nelson who makes no claim to be certified project planner or anything of the sort. It is based on his understanding of project management after 25 years of software development. [#Contributors Other developers] have also offered some hints and useful comments (according to their experience) in order to enhance this page, and get a better understanding of the features and requirements needed. == Contributors == - Olemis Lang