Changes between Version 41 and Version 42 of ProjectManagementIdeas


Ignore:
Timestamp:
May 1, 2009, 1:39:18 AM (15 years ago)
Author:
Chris Nelson
Comment:

Finish calendar notes, relevel outline

Legend:

Unmodified
Added
Removed
Modified
  • ProjectManagementIdeas

    v41 v42  
    6767The essential property of a milestone is its date.  Trac tickets which are part of a milestone are implicitly due by the milestone date.  In general project management, milestones have FS dependency with some some tasks.  Together with dependencies between tasks, this dictates when tasks must be done to keep a project on schedule.
    6868
    69 = Task Scheduling =
     69== Task Scheduling ==
    7070
    7171The basic answer to "When will my project be done?" is generally ''displayed in'' a [http://en.wikipedia.org/wiki/Gantt_chart Gantt chart] which shows tasks, their dependencies, their duration (scaled by resource availability), and milestones.  [http://groups.google.com/group/trac-users/browse_thread/thread/83c0b6a248040542?hl=en Two] [http://groups.google.com/group/trac-users/browse_thread/thread/3084796acbc7233c/3f393a18f99cfebd?hl=en&tvc=2#3f393a18f99cfebd}}} threads] on the Trac Users mailing list, suggest that a Gantt chart is a fundamental requirement for project management but scheduling tasks is even more fundamental and a necessary precondition for producing a Gantt chart.
     
    119119Knowing that the schematic takes 3 days, we have to start by May 2 to finish on time.
    120120
    121 = Calendar =
    122 
    123 The schedule above isn't accurate unless we have a 7-day work week.  If we assume that the work week is Monday to Friday with Saturday and Sunday off, firmware has to finish Friday, May 8 and schematic has to finish Friday, May 1 so the project must begin April 29.
    124 
    125 = Gantt Charts =
    126 == Dependency and Duration ==
     121== Calendar ==
     122
     123The schedule above isn't accurate unless we have a 7-day work week.  If we assume that the work week is Monday to Friday with Saturday and Sunday off, firmware has to finish Friday, May 8 and schematic has to finish Friday, May 1 so the project must begin April 29.  Applying calendar information, our task list looks like the following.
     124
     125||'''ID'''||'''Summary'''||'''Estimate'''||'''Blocked by'''||'''Due'''||
     126||1||Design the Schematic||24h||||May 1, 2009||
     127||2||Design the Circuit board||16h||1||May 8, 2009||
     128||3||Design the packaging||16h||||May 8, 2009||
     129||4||Write firmware||40h||1||May 8, 2009||
     130||5||Assemble units||8h||2,3,4||May 11, 2009||
     131
     132== Gantt Charts ==
     133=== Dependency and Duration ===
    127134
    128135Once we have a task scheduler, we can simplify presentation of task scheduling with a very basic Gantt that showed just tasks and their dependencies and the resultant schedule.
     
    140147This requires only that the ticket have some information about estimated effort or duration of the task and simple FS task dependency.
    141148
    142 == Progress ==
     149=== Progress ===
    143150
    144151If we also track work on tasks, we can monitor project progress at a glance.
     
    146153[[Image(gantt-progress.PNG)]]
    147154
    148 == Resource Allocation ==
     155=== Resource Allocation ===
    149156
    150157When a resource is not available 100% of the time, tasks take longer than the work suggests.  By assigning effort to resources, we can chart this time dialation.
     
    154161When the hardware and software engineers are only available half time, the project gets delayed.
    155162
    156 == Critical Path ==
     163=== Critical Path ===
    157164
    158165Some tasks affect project schedule and some do not.  The tasks which affect the schedule are on the ''critical path''.
     
    162169Packaging design and circuit board layout are so short -- relative to other activities -- that speeding them up doesn't really help the project.  But if we could shorten schematic design or firmware, every day we take out of one of those activities we also take out of the project schedule.
    163170
    164 == Sub-tasks ==
     171=== Sub-tasks ===
    165172
    166173To manage the complexity of the chart, we can break tasks down into sub-tasks and show various levels of detail.
     
    170177[[Image(roll-up-2.PNG)]]
    171178
    172 == Progress Line ==
     179=== Progress Line ===
    173180
    174181A Gantt chart often includes a "today" line to show where a project stands.
     
    178185Bumps to the left indicate tasks that are behind schedule.
    179186
    180 == Slack Time ==
     187=== Slack Time ===
    181188
    182189A Gantt chart may also show slack time for tasks, how much they can slip before affecting the overall schedule.
     
    186193The black bars extending from the bottom of circuit board and packaging design indicate how much those tasks can slip without affecting deliverable.
    187194
    188 = Resource Utilization =
     195== Resource Utilization ==
    189196
    190197There are several views of resource utilization which may be helpful: