Change heuristic to determine the start date of a milestone
| Reported by: | Filipe Correia | Owned by: | |
|---|---|---|---|
| Priority: | normal | Component: | SumStatsPlugin |
| Severity: | normal | Keywords: | |
| Cc: | Filipe Correia | Trac Release: |
Description
For the first milestone, consider the start date on the date of the first ticket of that miletone instead of the current date.
Attachments (0)
Change History (3)
comment:1 Changed 13 years ago by
comment:2 Changed 13 years ago by
| Status: | new → assigned |
|---|
comment:3 Changed 7 years ago by
| Owner: | Rob Guttman deleted |
|---|---|
| Status: | assigned → new |
Note: See
TracTickets for help on using
tickets.



I've created a fake "milestone0" with the completion date set to the date that I want milestone 1 to start at. But this is not optimal. And it took me a while to find out this was a way to work around the issue.