Change heuristic to determine the start date of a milestone
Reported by: | Filipe Correia | Owned by: | |
---|---|---|---|
Priority: | normal | Component: | SumStatsPlugin |
Severity: | normal | Keywords: | |
Cc: | Filipe Correia | Trac Release: |
Description
For the first milestone, consider the start date on the date of the first ticket of that miletone instead of the current date.
Attachments (0)
Change History (3)
comment:1 Changed 12 years ago by
comment:2 Changed 12 years ago by
Status: | new → assigned |
---|
comment:3 Changed 6 years ago by
Owner: | Rob Guttman deleted |
---|---|
Status: | assigned → new |
Note: See
TracTickets for help on using
tickets.
I've created a fake "milestone0" with the completion date set to the date that I want milestone 1 to start at. But this is not optimal. And it took me a while to find out this was a way to work around the issue.